Control of density backfill in the process of the device of the storm sewer at building a shopping center on Brovarsky Avenue in Kyiv
- Name of work – “Implementation of control density backfill in the process of the device of the storm sewer at building a shopping center on Brovarsky Avenue in Kyiv”
The start and end dates October 2013 – July 2013.
Customer – LLC “DAKHMONTAJREBUD”
Main stages:
– Familiarization with available technical documentation.
– Perform of field investigations layered soil backfill (sampling,calibration of the penetrometer, density determination rapid method 126).
– Laboratory studies based on selected samples of 30 PCs.
– Processing of materials field and laboratory research.
– Preparation of report with conclusions and recommendations.
– To be able to use the rapid method under field conditions using a special device-pentrometer that are based on such components: a dynamometer, a dial indicator and rod with a corresponding conical nozzle.
5. As results of studies of folding it was completed corresponding report. The research was performed with the use of field and laboratory methods involving sampling for laboratory processing, layer-by-layer density test of soil backfill via express methods. In case of confirmation of the proposed project and relevant requirements of state Standards of density of soil backfill signed the established sample, the tripartite acts gave the right to the front opening for the following process.