State "Research institute of building production named of V.S. Balitsky" (Кyiv)

Beskyd tunnel

Comparative analysis of volume changes and cost of work during the construction of the Beskyd tunnel on the stage of working documentation in comparison with the stage of tender offer and analysis of the basis for the implementation of the relevant value adjustments

The work was performed by specialists of the sector of economic methods of management of construction of SE “RIBP” under the leadership of C. E. S., senior researcher, associate Professor Vakhovych Inna Volodymyrivna.

Customer: CJSC “Interbudmontazh” .

The aim of this work was to verificate changing the actual volume and cost of works on the temporary and permanent fastening of the tunnel in the construction of the Beskyd tunnel on the stage of working documentation in comparison with the stage of the tender offer.

The work included the following stages:

  • analysis of changes in the volume of works on the temporary and permanent fastening of the tunnel in the project at the stage of working documentation in comparison with the stage of the tender offer;
  • comparative analysis of changes in the cost of works on the temporary and permanent fastening of the tunnel in the project at the stage of working documentation in comparison with the stage of the tender offer;
  • analysis of the legal grounds for implementation of appropriate adjustments of cost of the executed works.

As a result of work it was provided to the customer an expert opinion on the legal basis of compensation for additional costs incurred due to unforeseen geological conditions in the design and construction of the “Beskyd tunnel”.